Tempe Academy of International Studies
Welcome to the construction website for Tempe Academy of International Studies

PROJECT DESCRIPTION:

Tempe Academy of International Studies will be undergoing a complete school renovation while on an active campus and will be performed in multiple phases. The school will be including two new buildings. The new buildings will be single-story buildings which will blend with the existing structures.

The rebuild portion will also include a new administration and learning commons building, a new cafeteria building with a kitchen and several new classrooms. The project will include ample opportunity for natural daylight in each space, polished concrete floors and carpet use, as well as outdoor dining and learning spaces. There will also be a parent drop-off area with longer queuing areas and more parking opportunities.

We will have a Contractor’s in the Classroom program with Tempe Academy, but we are still designing what this program will look like for the IB students.

 

CONSTRUCTION DURATION: May 2020 - Summer 2021

 

PROJECT CONTACTS:

Concord General Contracting:

Doug Strom, Project Manager: 480.694.2123

Ted Knisely, Senior Project Superintendent: 480.964.8465

Tempe Elementary School District:

Courtney Quesada: 480.730.7100

Project News
August 5, 2020
‘A’ Building: Underslab utilities are ongoing. Stage concrete stem walls have been poured. Steel structural columns in place. ‘B’ Building: Concrete building slab poured, and joints cut. ‘C’ and ‘D’ Buildings: Cabinets installed, coun
Read More
July 16, 2020
Buildings A and B – Footings and stem walls are complete.The under-slab plumbing and electrical are being installed as well. Building A – Grease interceptor in the kitchen was installed. Buildings C and D – Classroom remodel work is
Read More
June 16, 2020
Existing ductwork in the gymnasium has been removed.  New ductwork and lights will be installed. Existing locker rooms are being demolished.  Existing exterior walls are being saw cut for new windows and doors. Existing gymnasium lobby toilet room
Read More
May 15, 2020
Earthwork contractor is on site performing over-excavation. Testing engineer is making visits to inspect the earthwork process. Underground utility contractor is on site reworking existing flood irrigation lines. Demolition contractor on site.  Sele
Read More
[/vc_column]
[/vc_row]

Construction Schedule

Videos

Construction In The Classroom