‘A’ Building:

  • Underslab utilities are ongoing.
  • Stage concrete stem walls have been poured.
  • Steel structural columns in place.

‘B’ Building:

  • Concrete building slab poured, and joints cut.

‘C’ and ‘D’ Buildings:

  • Cabinets installed, countertops yet to be installed.
  • Flooring in classrooms start next week.
  • Ceiling tile grid patched, cut tiles being installed.
  • Classrooms painted. Window and door frame repainting is scheduled.
  • Wall and floor tile installation complete in C toilet rooms. D toilet rooms scheduled to finish next week.
  • Landscaping at College and Broadmor complete, awaiting sod.

‘E’ Building:

  • New ductwork in gym complete. Painting is scheduled.
  • Fire sprinkler piping being installed in the gym.
  • Final demolition in the old locker room areas finishing up.
  • Structural roof framing modifications at north and south roofs is complete.
  • All old rooftop mechanical units have been removed, all new have been set.
  • Roofs have been dried in.