• Buildings A and B – Footings and stem walls are complete.The under-slab plumbing and electrical are being installed as well.
  • Building A – Grease interceptor in the kitchen was installed.
  • Buildings C and D – Classroom remodel work is underway. The plumbing for new sinks, new electrical in-wall conduit and a new site sewer line are complete. Wall patching is underway. The toilet room wall and floor tile work is set to begin soon.
  • Building E – Interior demolition is ongoing. The existing interior concrete floor slabs in old locker room areas are being removed.  All new exterior window and door openings have been cut and are being removed.  New ductwork in the existing gym is being installed.  Existing exterior concrete walkway around Building E is being removed.