• Site security fencing in place.
  • Demolition of existing buildings 1001, 1007 and 1011 continuing on.
  • Site demolition of existing on-site asphalt paving being removed.
  • Abatement complete in 1008 building.
  • Mechanical, plumbing, electrical and fire alarm make-safe planning underway for 1008, 1009 and 1010 buildings.
  • Scheduling of interior demolition in 1008, 1009 and 1010 being scheduled.